Il collaudo del deumidificatore andrebbe effettuato
contestualmente a quello dell’impianto a pannelli in
funzionamento estivo; la principale verifica da effettuare
riguarda la portata dell’acqua di rareddamento che dovrebbe
essere di circa 240 l/h (*) quando la temperatura dell’acqua è
di circa 15 °C. Con temperature dell’acqua più basse, anche le
portate devono essere inferiori.
Nel caso in cui non sia possibile misurare la portata dell’acqua
vericare tale condizione controllando la temperatura dell’aria
in mandata accertandosi che:
- ci si trovi nelle condizioni di progetto;
- la macchina sia accesa da almeno 15 minuti;
- siano trascorsi almeno 10 minuti dall’ultima variazione di
portata dell’acqua.
Vericare che la temperatura dell’aria in mandata abbia lo
stesso valore della temperatura in aspirazione (macchina
neutra) ovvero al valore di progetto desiderato.
Taria in mandaTa = Taria in aspirazione = Valore di progeTTo
Per raggiungere tale obbiettivo agire sulla portata dell’acqua
variando l’apertura della valvola dell’acqua refrigerata.
(*)
Valore di portata con intervallo ammesso tra il +20%
e il -20% rispetto al valore indicato.
Una portata d’acqua inferiore a 185 l/h può inibire il
funzionamento o danneggiare la macchina.
The dehumidier must be tested together with the panel system in
summer operating mode; the main check which must be performed
regards the cooling water ow rate which must be approximately
240 l/h (*) when the water temperature is approximately 15 °C.
By using lower temperatures, water ow rates will be inferior too.
In the event that it is not possible to measure the water ow rate,
verify the condition by checking the delivery air temperature,
ensuring that:
- it is within the project conditions;
- the machine has been on for at least 15 minutes;
- at least 10 minutes have passed since the last water ow rate
variation.
Check that the delivery air temperature has the same value as the
intake temperature (machine neutral) i.e. the desired project value.
TdELIVERY AIR = TINTAkE AIR = PROjEcT VALuE
In order to reach this objective, adjust the water ow rate, varying
the opening of the chilled water valve.
(*)
Flow-rate may vary between +20% and -20% than the
reported value.
If the water flow-rate is lower than 185 l/h may affect the
functioning or even damage the unit.
Esempio:
T
aria ingresso: 26°C
Taria in uscita: 26°C
Umidità relativa: 65%
Tacqua: 15°C
Portata batterie: 240 l/h
Example:
T incoming air: 26°C
T outgoing air: 26°C
Relative Humidity:
65%
Twater: 15°C
Coil ow rate: 240 l/h
1
2
Dopo aver riempito d’acqua l’impianto è
obbligatorio sfiatare dell’aria lo scambiatore
interno.
After having lled the system with water, the internal
exchanger must be bled with air
3 START-uP ANd TESTING - AVVIAMENTO E COLLAUDO