11. Installation
24
117592 03/2013
11.2 Mechanical installation
a) Preparation before
installing the columns
Identify the columns with the help of the latches
on the mechanical safety system: The primary
column is fitted with one cable clamp for the
latch control cable (Fig. 19).
19
Before installing the preassembled columns,
mark out the outer distance between columns of
3320 mm on the floor to help you. Then align
the columns with this (Fig. 18).
Place the two columns on the floor at the
installation site.
Now run in the synchronisation cables and the
latch cable before aligning the columns
according to the diagram in Fig. 22.
b) Assembling the columns
Use a piece of wood (from the packaging) to
support the slider block 10 cm above the base
plate. Use suitable lifting gear and handling
equipment to set up the two columns in their
upright position.
Make sure that the cylinders stand properly in
the column.
c) Floor anchoring
CAUTION
Select the installation location
Do not assemble the lift on asphalt or similar
unstable surfaces. The columns are only held
in the floor by anchors.
The concrete should have a compression
strength of at least 20 N/mm² and a minimum
thickness of 200 mm to achieve a minimum
anchoring depth of 105 mm.