Copyright © 2021 Axxiom Manufacturing, Inc.
8.12 VBS II Blowdown System: Remove monthly and check for internal wear of components.
Replace worn components as needed. See drawing in Section 9.10.
8.13 PPE: Check daily to verify that all personal protective equipment is available for each blast
operator. Check daily to verify that all personal protective equipment is in good operating
condition. Consult the operating and maintenance instructions provided by the manufacturer of
each PPE item. See Section 3.10 and reference OSHA 29 CFR 1910 Subpart I.
Failure to use personal protective equipment could result in serious injury or death.
8.14. Warning Decals: Check monthly to verify that all the warning decals are in position and
legible. See Section 0.0 for full descriptions and locations.
Failure to maintain warning decals risks the possibility of not alerting the abrasive blaster
operator to potential dangers which can result in serious injury or death. See Section 0.0.
8.15. Handway Assembly: Refer to Section 6.3 for installation and inspection procedures.
8.16. Moisture Separator and Strainer: With the air supply on, once a day completely open the
moisture separator drain ball valve (#8) and the control air strainer petcock (#23) to purge all
moisture and debris. Purge for about one minute then close the ball valve and petcock.