Installation of an SP PRO Powerchain System
Introduction
This installation note will demonstrate how to install and configure SP PRO units in a Powerchain system,
either as a single phase, three phase or split phase system with up to three worker units per phase (four
SP PRO inverters per phase – one manager, with three worker units).
Preparation
• This document needs to be read in conjunction with the SP PRO Instruction Manual and SP LINK
instruction manual (both found in the SP LINK Help menu)
Powerchain Definitions
• System Manager – Must be connected to L1 – all configuration, control and interaction is via this
SP PRO
• Phase Manager – Main SP PRO on L2, L3 and/or Split(180°)
• Worker – any other SP PRO within system on any phase.
Summary of steps
The following is a summary of the steps required to complete the installation. Once the installation is
completed, use the outline below as a check list:
Installation step
Pages
1
Install the SP PROs, including the DC and AC wiring.
2 - 6
2
Install and Configure the Batteries
(DC Power to the SP PROs is required to complete the process)
3
Connect the SP PRO SYNC connections and terminators
7
4
Verify Firmware
8
5
Create the configuration for the SP PRO Powerchain system, using the
Site Configuration Wizard in SP LINK
9
6
Connect to the SP PRO System Manager via SP LINK, assign the SP PROs
in the Powerchain system and save the configuration
11
7
Test the system function
12