IN0016 Revision 12 Part # 004573 – 1 of 22
POWER PERFORMANCE PASSION
SP PRO Three Phase
Installation Notes
SP PRO - Three Phase Installation Notes
For SP PRO Firmware revision 7.01 and above.
Contents
SP PRO - Three Phase Installation Notes ............................................................................... 1
Introduction ..................................................................................................................... 2
Installation checklist .......................................................................................................... 3
Wiring Overview ............................................................................................................... 6
Installation ..................................................................................................................... 10
Charge Stage Linking ................................................................................................... 13
SP PRO Configuration – Additional Configuration Settings .................................................. 13
System – Multiple Phase Settings ................................................................................. 13
Verifying Phase Settings ............................................................................................... 14
System – Multiple SP PRO Charging .............................................................................. 15
Charge Stage Linking ................................................................................................... 15
Test Linking (Test linking of charge stages) .................................................................. 16
Shunts ........................................................................................................................ 17
Zero all current shunts ................................................................................................. 18
Test shunt 1 ................................................................................................................ 18
SoC Control ................................................................................................................. 18
Battery Capacity .......................................................................................................... 18
Max. Charge Current .................................................................................................... 18
Battery Charger Voltage settings and Temperature Compensation .................................. 18
DC Shutdown and Generator Lock Out Override ............................................................ 19
Disable Generator Control on L2 and L3 ........................................................................ 19
AC Source Power ......................................................................................................... 20
Test System Function .................................................................................................. 20
Solar Hybrid Control .................................................................................................... 21
Synchronising SoC between inverters. .......................................................................... 22
Operation ....................................................................................................................... 22
Additional Information ..................................................................................................... 22