12-pulse series connection
4.3 Commissioning
12-pulse applications
40 Compact User Manual, 09/2015, A5E34871844H
4.3.2
Carrying out commissioning
Commission the master converter
and
the slave converter as described in the SINAMICS
DCM DC converter operating instructions (commissioning steps 1 up to and including 8):
When commissioning with the BOP20 operator panel:
Perform commissioning steps
When commissioning with the AOP30 operator panel:
Execute "Drive commissioning" menu command
When using the STARTER commissioning tool for commissioning:
Start the project wizard
n+m mode
For a 12-pulse series connection, restricted redundant operation is possible. With the setting
p51803 = 1, if a slave fails (devices with setting p51800 = 23 or 24) then, depending on the
minimum number of power units (set in p51802), this is tolerated. Master devices (12 pulse -
master p51800 = 21, or 12 pulse slave - p51800 = 22) must remain operational. The drive is
shut down if one of the two fails. It is not possible to transfer the master and redundancy of
armature and field (setting, p51803 = 2) is not possible. If the electronic supply fails, or
devices are removed with active bus terminating resistor, then for the device in front, the bus
terminating resistor should be activated using p51801 = 1. When reinstalling the previously
removed device, the change must be appropriately undone (p51801 = 0).

Other manuals for Siemens SINAMICS DCM

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SINAMICS DCM and is the answer not in the manual?

Siemens SINAMICS DCM Specifications

General IconGeneral
BrandSiemens
ModelSINAMICS DCM
CategoryMedia Converter
LanguageEnglish

Related product manuals