Commissioning
4.2 Commissioning with BOP-2 operator panel
SINAMICS G120C converter
30 Getting Started, 04/2014, FW V4.7, A5E34264105B AA
If you intend to commission the converter with IOP operator panel
The IOP offers commissioning wizards and help texts for an intuitive commissioning. For
further information refer to the IOP operating instructions.
If you intend to commission the converter with PC tool STARTER
Overviev of the most important steps:
1. Connect the PC to the converter via USB and start the STARTER tool.
2. Choose the project wizard (menu "Project / New with assistent").
In the project wizard choose "Find drive units online".
Select USB as interface (Access point of the application: "DEVICE …", interface
parameter assignment used: "S7USB").
Finish the project wizard.
3. STARTER has now created your project and inserted a new drive.
Select the drive in your project and go online
.
In your drive open the "Configuration" mask (double click).
Start commissioning with the "Assistent" button.
For further information refer to converter operating instructions.
4.2
Commissioning with BOP-2 operator panel
Installing the basic operator panel BOP-2
Procedure
For installing the BOP-2 operator panel you have to proceed as follows:
1.
Remove the blind cover from the converter.
2.
Place the bottom edge of the BOP-2 casing into the lower
recess of the converter housing.
3.
Push the BOP-2 towards the converter until the release-
catch clicks into place on the converter housing.
The BOP-2 is installed. When you supply the voltage to the converter, the operator panel
BOP-2 is ready to operate.