Installation
SITRANS LC300
10 Operating Instructions, 05/2021, A5E47904073-AA
4.2
4.3 Pressure Equipment Directive, PED, 97/23/EC
Siemens Level Transmitters with flanged, threaded, or sanitary clamp type process mounts
have no pressure-bearing housing of their own, and therefore do not come under the
Pressure Equipment Directive as pressure nor safety accessories (see EU Commission
Guideline 1/8 and 1/20).
SITRANS LC300 as supplied in the standard probe lengths is normally mounted on the vessel
top or through the tank wall at the detection level (if used as Point Level switch).
The cable version is designed for top mounting. The cable suspends vertically so that it
reaches into the process with the end of the cable being the start of the measurement
(dependent on probe option).
4.4
4.5 Handling Precautions
WARNING
To prevent damage, all LC300 units with a rod longer than 2 m (6.5 ft) must be handled as
described below.
When lifting LC300 from a horizontal position, support it at these three points:
Towards the end of the rod
Midway along the rod
At the process connection or flange