Sirona Dental Systems GmbH 1 Preparations
Installation Requirements C5
+
, C5
+
Tur n
60 27 978 D3415
D3415.021.03.08.02
11
Supply above the floor, "above-floor installation"
The supply pipe ends, corner valves and cables must be
routed as shown above.
The retrofit kit for above-floor installation (REF 33 17 265)
is required for installation.
For cleaning, flush the air and water pipes thoroughly (metal
chips!).
Supply through the floor, "underfloor installation"
1. The top edges of the corner valves for air and water
must not protrude more than 60mm above the upper
surface of the finished floor.
2. The suction and drain pipes must be flush with the up-
per surface of the floor (a deviation of +5mm is permis-
sible).
Internal diameter for both pipes: 36,5mm.
3. The electrical cables must protrude at least 500mm.
Supply lines in the termination panel