3. To deactivate communication via BLUETOOTH,
set the rotary switch C to position 0 using a flat-
blade screwdriver (blade width: 2.5mm). This
will protect your PV system from unauthorized
access.
The inverter will adopt the setting after commissioning. This can take up to five minutes.
7.4 Commissioning the Inverter
Requirements:
The inverter must be correctly mounted.
The circuit breaker must be correctly rated.
All cables must be correctly connected.
Unused DC inputs must be sealed using the corresponding DC connectors and sealing plugs.
The country data set must be set correctly for the country or the purpose.
Procedure:
1. Mount the enclosure lid:
Fit one conical spring washer to each
screw. The grooved side of the conical
spring washer must face the screw head.
Position the enclosure lid with the six screws
on the enclosure and tighten all screws in
the sequence 1 to 6 using an Allen key
(AF5) (torque: 6Nm ± 0.5Nm).
The teeth of the conical spring washer
press into the enclosure lid. This ensures
that the enclosure lid is grounded.
2. Secure the protective cover using two screws and an Allen key (AF5).
3. Securely plug in the ESS.