13.1 Inspection
Please follow the inspection instruction below:
Interval
Instruction
Once per year
Check the door tightness, cable bushings, MDU protective cabinet and
control panel’s ventilation device
Once per year
Check the tightness of tap-changer head cover, protective relay and
all pipes’ connectors.
Once per year
Check the MDU’s protective cabinet and if the heater inside
the control panel works normally or not.
Once per year
Check if the protective relay functions normally.
Once per year
Check whether the silica gel desiccant in the transformer oil
conservator is working properly
Once per year
or every 20000 operations
Check the oil sample. If it doesn’t meet the parameters in Table 13-2,
it’s recommended to change the transformer oil.
Table 13-1 Inspection instruction
Item
Breakdown voltage
Water content
Limit values for insulating oil in accordance with IEC 60296
When commissioning the transformer for the first time
60kV/2.5mm
15ppm
During operation
Class I tap-changer
30kV/2.5mm
40ppm
Class II tap-changer
40kV/2.5mm
30ppm
After maintenance
45kV/2.5mm
15ppm
Limit values for natural esters in accordance with IEC 62770
When commissioning the transformer for the first time
60kV/2.5mm
≤100ppm
During operation
Class I tap-changer
30kV/2.5mm
≤200ppm
Class II tap-changer
40kV/2.5mm
≤200ppm
After maintenance
45kV/2.5mm
≤100ppm
Table 13-2 Oil sample limit values