COMMISSIONING THE INVERTER
HYD 5K...20KTL-3PH 85
6 Commissioning the inverter
6.1 Safety test before commissioning
ATTENTION
Check the voltage range
Ensure that the DC and AC voltages are within the
permissible range of the inverter.
6.2 Double Check
Please ensure that the inverter and all the wiring are installed
correctly, securely, and reliably, and that all environment requirements
are met.
1. Inverter is firmly fastened to the mounting bracket on the wall.
2. PV+/PV- wires are firmly connected, polarity and voltage are
correct.
3. BAT+/BAT- wires are firmly connected, polarity and voltage are
correct.
4. DC isolator is correctly connected between battery & inverter, DC
isolator: OFF.
5. GRID / LOAD cables are firmly / correctly connected.
6. AC circuit breaker is correctly connected between inverter GRID
port & GRID, circuit breaker: OFF.
7. AC circuit breaker is correctly connected between inverter LOAD
port & critical load, circuit breaker: OFF.