Adding, Removing, or Replacing Power Optimizers
1.
Turn OFF the inverter ON/OFF switch, and wait until the LCD indicates that the DC
voltage is safe (<50V), or wait five minutes before continuing to the next step.
WARNING!
If you cannot see the inverter panel, or if a malfunction is indicated on the
LCD panel, wait five minutes for the input capacitors of the inverter to
discharge.
2. Turn OFF the DC Safety Unit (if applicable).
3. Disconnect and connect the necessary power optimizers.
4. Perform pairing and other procedures described in
Commissioning the Installation
on page 36 on all inverters to which power optimizers were added or from which
power optimizers were removed.
5. In the monitoring platform, use the Replace button in the logical
layout tab (in site Admin). Replace the serial number of the removed
power optimizer with the serial number of the newly installed power
optimizer. Refer to https://www.solaredge.com/sites/default/files/se-
monitoring-portal-site-admin.pdf
Appendix F: Replacing and Adding System Components 97
Three Phase System Installation Guide MAN-01-00057-4.1

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SolarEdge SE4000 and is the answer not in the manual?

SolarEdge SE4000 Specifications

General IconGeneral
ModelSE4000
ManufacturerSolarEdge
Rated AC Power4000 W
CEC Weighted Efficiency97.5%
Number of MPP Trackers1
Protection RatingIP65
CoolingNatural Convection
Warranty12 years
AC Output Power4000 W
AC Voltage220 / 230 / 240 Vac
Max. DC Input Power5400 W
Operating Temperature Range-25°C to 60°C

Related product manuals