Site Preparation Checklist
Use this checklist to ensure that all of the requirements have been met prior
to delivery of your library.
Site Requirements
Data Center Flooring on page 19
Flooring is hard (not carpeted) and capable of supporting the weight of the
library.
Weight distribution plates have been installed (optional).
Flooring is level.
Space Requirements on page 21
Space is available for the library’s height, width, and depth.
Space is available for service and operator access.
Space is available for future growth (optional).
Cables can be routed to the library’s cable access areas.
Power Requirements on page 25
Electrical and peripheral equipment cabling is complete and organized.
Proper number and type of outlets are available at the required locations.
Electrical circuits meet power consumption requirements.
Two separate branch circuits, meeting the power requirements, are available to
allow for failover in the event of a power failure in one of the circuits (optional).
Network Cabling Requirements on page 30
Cabling for remote access to the library’s BlueScale web interface is complete
and organized.
Cabling for host access to the library is complete and organized.
Cabling for host access to the tape drives is complete and organized.
Cabling for access to the BlueScale Vision Camera(s) is complete and organized.