Site Preparation Checklist
February 2019 Site Preparation GuideSpectra T950B Library
40
Environmental Requirements on page 32
Airflow and air quality meet the library’s specifications.
Temperature and humidity are within the library’s specifications.
Fire suppression equipment is in place (optional).
Vibration and shock will not exceed the library’s specifications.
Preparing for Installation
Receiving and Storing the Library on page 35
The receiving/storage area can handle the size and weight of each crated library
frame as well as the crate(s) of library components.
The delivery and installation schedule allows 24 hours for the library to
acclimate before installation.
Unpacking and Moving the Library on page 36
Floors to be traversed can handle the weight of the crated frames.
Transportation equipment—forklift, pallet jack, and/or stair crawler—is available
and can handle the weight of the crated frames.
Doorways, stairwells, hallways, and elevators allow the size of the crated library
without tilting.
Elevators can handle the weight of the crated library.
Space is available in the data center where the library is to be installed for the
crates and crate ramp, with extra space for maneuvering.
If the path, transportation equipment, or data center is not able to
accommodate the crates, contact Spectra Logic Professional Services in advance
of the installation date. See Contacting Spectra Logic on page 8.