Not to be distributed without prior consent of SPI Lasers UK Ltd.
Slide: 3
FS-S00149-Rev A
Before the redPOWER PRISM OEM laser is delivered to the customer, the customer must ensure that the following
Utilities are available.
• Water Supply : Cooling Water Requirements
• Integrators must ensure that the water condition meets the requirements set out in the following tables and in
the manual below.
• SM-S00481 redPOWER Prism OEM Fibre Laser Instructions for Use
• Ensure that the hose connections are leak free and tested before electrical operation of the laser .
• SPI recommend that an appropriate filter is installed in line to the flow lines of the laser. The grade of filter is
100µm
• Pre-treated water and additives for prevention of corrosion, scaling and microbial growth are available
commercially, for example from NALCO and Optishield.
• additives may reduce the heat capacity of the water. The flow rate must be increased to compensate.
• The following table will show the specification for the chiller to ensure correct cooling of the OEM and PIPA-Q
BDO head.
Customer Requirements Pre Install
Water Supply & Fittings
29/06/2016
Flow from Chiller
or House Water
Return to Chiller or
House Water