EasyManuals Logo

SPI Lasers redPOWER User Manual

SPI Lasers redPOWER
19 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #3 background imageLoading...
Page #3 background image
Not to be distributed without prior consent of SPI Lasers UK Ltd.
Slide: 3
FS-S00149-Rev A
Before the redPOWER PRISM OEM laser is delivered to the customer, the customer must ensure that the following
Utilities are available.
Water Supply : Cooling Water Requirements
Integrators must ensure that the water condition meets the requirements set out in the following tables and in
the manual below.
SM-S00481 redPOWER Prism OEM Fibre Laser Instructions for Use
Ensure that the hose connections are leak free and tested before electrical operation of the laser .
SPI recommend that an appropriate filter is installed in line to the flow lines of the laser. The grade of filter is
100µm
Pre-treated water and additives for prevention of corrosion, scaling and microbial growth are available
commercially, for example from NALCO and Optishield.
additives may reduce the heat capacity of the water. The flow rate must be increased to compensate.
The following table will show the specification for the chiller to ensure correct cooling of the OEM and PIPA-Q
BDO head.
Customer Requirements Pre Install
Water Supply & Fittings
29/06/2016
Flow from Chiller
or House Water
Return to Chiller or
House Water

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SPI Lasers redPOWER and is the answer not in the manual?

SPI Lasers redPOWER Specifications

General IconGeneral
BrandSPI Lasers
ModelredPOWER
CategoryControl Unit
LanguageEnglish

Related product manuals