Before the redPOWER PRISM OEM laser is delivered to the customer, the customer must ensure that the following
Utilities are available.
Water Supply : Cooling Water Requirements
Integrators must ensure that the water condition meets the requirements set out in the following tables and in
the manual below.
SM-S00481 redPOWER Prism OEM Fibre Laser Instructions for Use
Ensure that the hose connections are leak free and tested before electrical operation of the laser .
SPI recommend that an appropriate filter is installed in line to the flow lines of the laser. The grade of filter is
100µm
Pre-treated water and additives for prevention of corrosion, scaling and microbial growth are available
commercially, for example from NALCO and Optishield.
additives may reduce the heat capacity of the water. The flow rate must be increased to compensate.
The following table will show the specification for the chiller to ensure correct cooling of the OEM and PIPA-Q
BDO head.
Customer Requirements Pre Install
Water Supply & Fittings
29/06/2016
Flow from Chiller
or House Water
Return to Chiller or
House Water