www.stromltd.com
STROM LIMITED 2020
26
Electric Boilers
WATER CONNECTIONS
FILLING POINT:
A convenient ll point has been added to the boiler called the “water replenishing valve”. A temporary connection
should be made to this point when initially lling the boiler or topping the water pressure up. This must be
closed once the system is up to pressure and the air has been purged. Alternatively, this can be left closed and a
traditional lling loop can be used for lling of the heating system and replacing any water lost during servicing
or bleeding the system. The lling loop should be installed in close vicinity to the boiler or connected to the water
replenishing connection. The lling loop should be installed to current water regulations and should be removed
after lling and the valves sealed with suitable caps.