Maglink LX
User Manual | Shift Report
Rev. 9, 04-2016
Page 29 of 40
10
S
HIFT
R
EPORT
The console can produce a Shift Report.
The shift report can be manually triggered or it can be automatically configured. You can configure multiple
daily Shift reports.
The following table shows the necessary procedure steps for managing such Shift Reports:
Step Description
1 Press the "INFO" button and access the relevant page
2
Press the button "Close shift report" and confirm the subsequent message (The current Shift
Report is closed with a new shift automatically started)
You can access the page "Shift Report" and view the daily Shift Report data of, as per paragraph 7.1.2.7
"Tank Details/Shift Report.”
If you have configured the automated Shift reports by manually pressing Closure of Shift Reports from the
Info Page this closes the Shift Report in progress and opens the next one which will then be automatically
closed at the next scheduled date.
If a delivery is in progress, the value of the final volume of the Shift Report is equal to the volume in tanks
prior to commencement of Delivery.