INSTALLATION
Note: U.S.D.A. approved equipment must use a food grade hydraulic fluid
with similar properties (Citgo Clarion FG ISO 68 or equal).
5. Install conduit suitable for four wires between the top right side of the control
panel (above the transformer) and the rear outer panel. Use wires that are the
same size or larger than the largest gauge wires in the control panel. Use clamp
type conduit bulkhead fittings with anti-chafe bushings.
6. Install three wires and a protective earth wire (see included electrical drawing for
wire size) from an appropriate power source through the conduit, leaving enough
wire inside the control panel to reach the top of the disconnect switch. Attach
the green protective earth ground wire to the ground terminal. Ground the pellet-
izer before use because static electricity can build up on the pelletizer under cer-
tain conditions.
7. Strip the proper amount (as recommended by the ferrule manufacturer) of insula-
tion from the wires and secure ferrules on the bare ends. Place ends in the termi-
nals at the top of the disconnect switch (DIS-1) and tighten securely. Close the
control panel and be sure the disconnect switch (DIS-1) is off.
8. Turn on the power at the power source. Turn on the disconnect switch (DIS-1) at
the control panel and press the START button. Observe the rotation of the elec-
tric motor. If the motor rotates in the same direction as the reference arrow on
the motor, the electrical connections are correct.
9. If the motor rotates in the wrong direction, press the STOP button. Turn off the
disconnect switch (DIS-1) at the control panel and disconnect the power source.
Open the control panel and swap any two leads at the top of the disconnect
switch (DIS-1). Be sure to tighten the terminal connections securely.
3.3
WARNING:
Be sure that the power source is
turned off.