G9000 TOSHIBA SYNC KIT 1000-2000kVA Installation Manual - 200151-001 7
Figure 4-1: Installation Procedures for MASTER UPS(1000-2000kVA)
Color of wires
A-phase: Yellow
B-phase: Blue
C-phase: White
Cable tie Mount
3xFuses,
Fuse holder
Field-installed
wires to
Slave UPS
To Output bus bars
Secondary side of
52SU, 52SV, 52SW
Wires between
Output bus bars(M4)
and fuse holder(M5)
Upper part of bypass cabinet
The connection in this portion is
same for all UPS (1000-2000kVA).