G9000 TOSHIBA SYNC KIT 1000-2000kVA Installation Manual - 200151-001 13
6 SLAVE UPS Setting Procedures
The setting for MASTER UPS is not necessary.
1. Before the UPS setting, install the metal cover plates for the UPS.
2. Keep door closed after the "MAINT" button located on the SW1 PCB
(DPAU-89*) is pressed.
6.1 Supply the AC input and the Bypass input voltage to the UPS.
Initialization will start. Under initializing, the UPS will automatically:
- Turn on contactor CB1;
- Initialize converter operation;
- Initialize inverter operation;
After initialization, LCD screen should appear.
(See also: G9000 SERVICE MANUAL)
6.2 Press the "MAINT" button located on the SW1 PCB (DPAU-89*). Maintenance screen will appear.
6.3 Press the "SETUP" tab on the Maintenance screen, and then press the "INPUT PORT" button.
6.4 Press the "IN3" button, and select item "9: ANOTHER BUS. SYNC." by pressing " " key.
6.5 Press the "OK" button, and confirm that "9: ANOTHER BUS. SYNC." is lay out.
6.6 Press the "MAINTENANCE" tab, and then press the "MAIN MENU" button for completion of SLAVE UPS
SETTING.
1. As the IN3 default setting, it may be BATT. TEMP. ABNL..
2. Before making a change of the IN3 setting, make sure that BATT. TEMP. ABNL. function is not
required.
(Contact Toshiba International Corporation, if BATT. TEMP. ABNL. function is under service.)
CAUTION
!
NOTE
!
NOTE