Checkout Procedures
The final phase of the installation is the system Checkout Procedures. The following list represents the most common items covered in a
Checkout Procedure. Confirm all requirements in this document have been met.
All wiring connections are tight and properly secured.
Voltage and running current are within limits.
Ductwork is sealed and insulated.
Supply registers and return grilles are open, unobstructed, and air
filter is installed.
Indoor blower and outdoor fan are operating smoothly and
without obstruction.
Indoor blower motor set on correct speed setting to deliver
required CFM. “Blower and fan set screws are tight.
Cover panels are in place and properly tightened.
System functions safely and properly in all modes.
Owner has been instructed on use of system and given manual.

Other manuals for Trane P0V0 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane P0V0 Series and is the answer not in the manual?

Trane P0V0 Series Specifications

General IconGeneral
BrandTrane
ModelP0V0 Series
CategoryBlower
LanguageEnglish

Related product manuals