SAFETY WARNING
Only qualified personnel should install and service the equipment. The installation, starting up, and servicing of
heating, ventilating, and air-conditioning equipment can be hazardous and requires specific knowledge and training.
Improperly installed, adjusted or altered equipment by an unqualified person could result in death or serious injury.
When working on the equipment, observe all precautions in the literature and on the tags, stickers, and labels that are
attached to the equipment.

Table of Contents

Question and Answer IconNeed help?

Do you have a question about the Trane Precedent YZC072F and is the answer not in the manual?

Trane Precedent YZC072F Specifications

General IconGeneral
Model NumberYZC072F
CategoryAir Conditioner
Cooling Capacity72, 000 BTU/h
EER11.2
HSPFNot Applicable
Voltage208/230V
Phase3
Frequency60 Hz
Compressor TypeScroll
RefrigerantR-410A

Summary

Introduction and Safety Guidelines

Warnings, Cautions, and Notices

Safety advisories throughout the manual guide safe operation and observance of precautions.

Field Wiring and Grounding Safety

Field wiring must be done by qualified personnel to avoid fire and electrocution hazards.

Personal Protective Equipment (PPE)

Technicians must wear proper PPE to protect against electrical, mechanical, and chemical hazards.

EHS Policies and Regulations

Stresses adherence to company EHS policies and local regulations for safety.

Model Number Description and Notes

General Information

Pre-Installation Safety

Fiberglass Wool Handling Safety

Warns about fiberglass wool hazards and details required PPE and first aid.

Dimensions, Weights, and Lifting Safety

Lifting Safety Precautions

Warns about lifting heavy objects and emphasizes proper equipment and testing.

Installation Procedures

Site Preparation and Structural Requirements

Covers foundation, ductwork, roof curb installation, and combustible material safety.

Unit Rigging and Placement

Provides instructions for rigging, lifting, and general unit installation checklist.

Electrical and Gas Supply Installation

Covers main electrical power requirements and through-the-base gas installation.

Pre-Start Procedures

Voltage, Phasing, and Component Checks

Explains voltage imbalance requirements and electrical phasing checks for motors.

Unit Startup Procedures