EasyManua.ls Logo

Trane SFHJ090-162 - Rigging the Unit; Main Electrical Power Requirements; Field Installed Control Wiring; Requirements for Gas Heat

Trane SFHJ090-162
200 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Installation
RT-SVX24J-EN 63
Rigging the Unit
[ ] Set the unit onto the curb; check for levelness.
[ ] Ensure unit-to-curb seal is tight and without buckles
or cracks.
[ ] Install and connect condensate drain lines to each
evaporator drain connection.
[ ] Remove the shipping hardware from each
compressor assembly.
[ ] Remove the shipping hold-down bolts and shipping
channels from the supply and exhaust fans with spring
isolators.
[ ] Check all supply and exhaust fan spring isolators for
proper adjustment.
[ ]Verify that all plastic coverings are removed from the
compressors.
[ ] Verify all discharge and liquid line service valves
(one per circuit) are back seated.
Main Electrical Power Requirements
[ ] Verify that the power supply complies with the unit
nameplate specifications.
[ ] Inspect all control panel components; tighten any
loose connections.
[ ] Connect properly sized and protected power supply
wiring to a field-supplied/installed disconnect and unit
[ ] Properly ground the unit.
All field-installed wiring must comply with NEC and
applicable local codes.
Field Installed Control Wiring
[ ] Complete the field wiring connections for the
constant volume controls as applicable. Refer to“Field
Installed Control Wiring” for guidelines.
[ ] Complete the field wiring connections for the
variable air volume controls as applicable. Refer to
“Field Installed Control Wiring” for guidelines.
Note: All field-installed wiring must comply with NEC
and applicable local codes.
Requirements for Electric Heat Units
[ ] Verify that the power supply complies with the
electric heater specifications on the unit and heater
nameplate.
[ ] Inspect the heater junction box and control panel;
tighten any loose connections.
[ ] Check electric heat circuits for continuity.
Requirement for Gas Heat
[ ] Gas supply line properly sized and connected to the
unit gas train.
[ ] All gas piping joints properly sealed.
[ ] Drip leg Installed in the gas piping near the unit.
[ ] Gas piping leak checked with a soap solution. If
piping connections to the unit are complete, do not
pressurize piping in excess of 0.50 psig or 14 inches
w.c. to prevent component failure.
[ ] Main supply gas pressure adequate.
[ ] FlueTubes clear of any obstructions.
[ ] Factory-supplied flue assembly installed on the unit.
[ ] Connect the 3/4" CPVC furnace drain stubout to a
proper condensate drain. Provide heat tape or
insulation for condensate drain as needed.
Requirements for Hot Water Heat
[ ] Route properly sized water piping through the base
of the unit into the heating section.
[ ] Install the factory-supplied, 3-way modulating valve.
[ ] Complete the valve actuator wiring.
Requirements for Steam Heat
[ ] Route properly sized steam piping through the base
of the unit into the heating section.
[ ] Install the factory-supplied, 2-way modulating valve
[ ] Complete the valve actuator wiring.
[ ] Install 1/2", 15-degree swing-check vacuum
breaker(s) at the top of each coil section. Vent
breaker(s) to the atmosphere or merge with return
main at discharge side of steam trap.
[ ] Position the steam trap discharge at least 12" below
the outlet connection on the coil.
[ ] Use float and thermostatic traps in the system, as
required by the application.
O/A Pressure Sensor and Tubing
Installation
(All VAV units and all units with Statitrac)
Figure 44, p. 66
O/A pressure sensor mounted to the roof bracket.
Factory supplied pneumatic tubing installed between
the O/A pressure sensor and
the connector on the
vertical support.
Field supplied pneumatic tubing connected to the
proper fitting on the
space pressure transducer located
in the filter section, and the other end routed to a
suitable sensing location within the controlled space.
Condensate Drain Connections
Each unit provides two 1-1/4" evaporator drain
connections on each side of the unit.
Due to the size of these units, all condensate drain
connections must be connected to the evaporator drain

Table of Contents

Related product manuals