Setting up the daily schedule
CNT-SVP01C-EN 51
the daily schedules. Another set of Start and Stop rows appears in the
daily schedule table.
Figure 36. Start and stop time examples
4. In the daily schedule table, click in the cell for the day-of-the-week
start time.
5. Type the time you want the occupancy to start.
Note:
The controller does not check event order. It always implements
the last commanded mode. This implies that you could have two
starts or two stops in a row in a single day. Figure 36 illustrates
some examples of event orders. For Example 3, assume that the
previous day ended with a start event. Example 4 shows the
schedule output in the case of two start and stop events in a
row. The second event of the same type is ignored.