Installations- och driftinstruktion Installation and Operation Manual
UV-system typ UBK UV sterilizer series UBK
© UEBERALL 2007
Sida / Page 1 / 13
Innehåll: Sida
Viktig information 2
Installation av UV-system 3
Installation av UV-sensor 5
Installation av kvartsglas 6
Installation av UV-lampa 7
UV-övervakning 8
Inställningar vid drifttagning 9
Underhåll 10
Felsökningsschema 11
Reservdelslista 13
Bilagor:
Kopplingsscheman
Måttritningar
Content: Page
Important Information 2
Installation of UV sterilizer 3
UV sensor installation 5
Quartz jacket installation 6
UV lamp installation 7
UV monitoring 8
Adjustments for start up 9
Maintenance 10
Fault Finding Table 11
Spare Part Lists 13
Appendix:
Wiring Diagrams
Dimensional drawings
UBK-1
UBK-2
UBK-3
UBK-4
Question and Answer IconNeed help?

Do you have a question about the UEBERALL UBK-2 and is the answer not in the manual?

Summary

Important Information Concerning Operation and Safety

Fragile Parts and Glass Surfaces

Handling delicate components like UV lamps, quartz jackets, and sensors. Avoid touching glass surfaces with bare hands.

Preconditions for Function and Warranty

Ensuring correct installation, operation, and matching water/power specifications for warranty validation and optimal performance.

Installation of UV Sterilizer

UV Radiation Chamber Installation

Instructions for installing the UV reactor into the piping system, referencing dimensional drawings for precise placement.

UV Sensor Installation

Procedures for installing the sensor window and sensor cartridge into the UV reactor assembly.

General Installation Guidelines

Key considerations for unit installation including orientation, service access, mounting, valve requirements, and pressure testing.

Quartz Jacket Installation

UV Lamp Installation

UV Monitoring and Start-up Adjustments

System Status Indicators

Explanation of system status indicators (LEDs) and factors affecting monitoring, such as lamp intensity and water transmission.

Start-up Adjustments

Procedures for adjusting the unit upon initial start-up using potentiometer and observing indicator lights.

Maintenance

Essential Maintenance Checks

Checks required for yellow or red alarm indicators, including cleaning quartz jackets and replacing UV lamps.

Resetting Operation Hour Meter

Procedure to reset the digital operation hour meter after replacing the UV lamp.

Fault Finding Table

Spare Part List