LPX SEED TREATER
TREATING SEED
1. Prime the line going to the atomizer by turning the Atomizer switch to ON and
turn the SEED TREATMENT valve to PROCESS. Next turn the pump direction
switch to FORWARD and the Hand / Off / Auto switch to Hand. Liquid should
begin pumping up to the atomizer. After the line has been primed, turn the
Hand / Off / Auto switch to Auto. Additional liquid can be pumped up into the
atomizer and into the drum to guarantee coverage of the first seed that passes
through the machine.
Do NOT pump liquid into the atomizing chamber when the
atomizer is OFF.
Ne pas pomper de liquide dans la chambre d'atomisation
lorsque le pulvérisateur est OFF.
2. Position the SEED TREATMENT SOURCE valve to MIX TANK.
If you desire to check the total ounces used per batch of seed. Fill
the calibration tube with the amount needed for the batch of seed
(about 10 ounces extra is a good practice). Then position the SEED
TREATMENT SOURCE valve to CALIBRATION TUBE and go on to
step 3.
Si vous désirez vérifier les totaux once utilisés par lot de semences.
Remplir le tube d'étalonnage avec la quantité nécessaire pour le lot
de semences (environ 10 onces supplémentaires est une bonne
pratique). Ensuite, positionner le TRAITEMENT DES SEMENCES
SOURCE vanne CALIBRATION tube et passez à l'étape 3.
3. Begin feeding seed into the Seed Wheel until the supply hopper is full. This will
ensure that the first pockets are full when the wheel is turned on. At this time,
ensure the seed gate on the seed treater is wide open. If there is no Seed Wheel
position conveyors, overhead hopper or seed box so the first seed coming into the
seed treater lands on the lower proximity switch which automatically turns on the
pump(s).
4. Turn the switches to ON for the Drum, Atomizer and any Conveyors being used.
Also turn the Hand / Off / Auto switch to AUTO. The pumps will not start until the
Seed Wheel switch has been activated (top of page 49).
! AVERTISSEMENT
NOTICE
AVIS