50 Installation and maintenance instructions 0020244997_07
13.7 Completing repair work
1. Establish the power supply.
2. Switch the product back on if this has not yet been
done. ( Page 32)
3. Install the front casing.
4. Open all service valves and the gas stopcock.
13.8 Checking the product for leak-tightness
Check that the product is leak-tight. ( Page 38)
14 Decommissioning
14.1 Temporarily decommissioning the product
Press the on/off button.
The display goes out.
Close the gas stopcock.
For products with domestic hot water generation and
products with a connected domestic hot water cylinder,
you must also close the cold-water isolation valve.
14.2 Permanently decommissioning the product
Press the on/off button.
The display goes out.
Disconnect the product from the power grid.
Close the gas stopcock.
Close the cold-water isolation valve.
Drain the product. ( Page 44)
15 Recycling and disposal
Disposing of the packaging
Dispose of the packaging correctly.
Observe all relevant regulations.
For detailed information refer to www.vaillant.co.uk.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Vaillant ecoTEC plus VU 6/5-5 Series and is the answer not in the manual?

Vaillant ecoTEC plus VU 6/5-5 Series Specifications

General IconGeneral
BrandVaillant
ModelecoTEC plus VU 6/5-5 Series
CategoryBoiler
LanguageEnglish

Related product manuals