5-114
BA TH412 * 06/2017 * 4512_5-14_Stilllegung_en.fm
5 Operation
Storing the battery
1. Remove the battery.
2. Clean the battery.
3. Charge the battery.
4. Store the battery in a dry and well-ventilated room at
around 20 °C.
5. Check the acid level once a month.
6. Charge the battery again before installing it.
Removing engine preservation
1. Remove the covers from the intake and exhaust
openings of the engine.
2. Remove the anti-corrosion agent from the pulleys.
3. Install the fan belt.
4. Drain the preservation oil and add engine oil.
5. Start up the engine.
6. Check the V-belt tension after running the engine for
two hours.
Putting the machine back into operation
1. Remove engine preservation.
2. Install the battery.
3. Check tire inflation pressure.
4. Remove the preservation from the piston rods of the
hydraulic cylinders.
5. Remove the machine from the jacks.
6. Check the operation of the electrical system.
7. Bleed the hydraulic system.
8. Check the operation of the steering and brakes.