Commissioning
Tests before commissioning 7.1
27
[en] | 02/2020 | 5100056064 | VP | Operator’s manual
7 Commissioning
7.1 Tests before commissioning
Information
Further information and detailed descriptions,
see Maintenance on
page 31
.
Perform the following checks:
Check machine and components for damage.
Do not put the damaged machine into operation. Damages and
defects must be repaired immediately.
Check fuel level.
Check fuel lines for leaks.
Check air filter.
Check engine oil level.
Check reversing starter.
7.2 Safety instructions for operation
WARNING
Tipping hazard due to slipping or overturning machine!
At least 2/3 of the machine must be on a stable surface near edges.
Take the machine out of operation and lift it back onto a stable sur-
face.
Operation on inclined surfaces
NOTICE
Technical damage due to failure of engine lubrication!
Do not exceed the maximum permissible inclination, see
see Tech-
nical data on page 42
.
Only approach gradients from below.
Ground conditions
The maximum dumping height depends on several factors of the ground
conditions. An exact specification of this value is not possible.
Determine the maximum fill height by compaction tests or soil
samples.
Shaking in cobblestones
To avoid damage to the machine or compaction material, use a slid-
ing device,
see Accessories on page 41
.
7

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson VP and is the answer not in the manual?

Wacker Neuson VP Specifications

General IconGeneral
BrandWacker Neuson
ModelVP
CategoryConstruction Equipment
LanguageEnglish

Related product manuals