5 Commissioning, tests, settings and maintenance
09.2019 25
ba-o.4.1.3-en-2.2-y
5.5 Documentation of changes to the cut-off point
WARNING
After testing of the new cut-off point, it must be documented in the cover of the device, in
the following table and in the crane logbook with signatures and confirmed.
Failure to document a change in the cut-off point will lead to immediate loss of the
warranty and is grossly negligent.
Setting
Reason for change
Operator's
signature
Service techni-
cian's signature
NOTICE
There is a page with a table as shown above at the end of these operating instructions.
This page can be taken out (or copied) and used to document changes to the settings of
the SLE 3 in the test book.
S1
S4
S2
S3
ON
Date _______________
Modified Setup
Device Rev._________
S1
S4
S2
S3
ON
Date _______________
Modified Setup
Device Rev._________
S1
S4
S2
S3
ON
Date _______________
Modified Setup
Device Rev._________
S1
S4
S2
S3
ON
Date _______________
Factory Setup
Device Rev._________

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Yale SLE 3 and is the answer not in the manual?

Yale SLE 3 Specifications

General IconGeneral
BrandYale
ModelSLE 3
CategoryControl Unit
LanguageEnglish

Related product manuals