Step 5 – Commissioning
• Check previous steps.
• Check the earth continuity (see below).
Upon installation or following service, the earthing continuity of the Hydroboil must be tested by a qualified
technician using a resistance meter of minimum accuracy of 5% full scale deflection.
• Isolate power supply.
• Verify meter ohms range, connect leads together, reading should be 0 ohms.
• Connect one test lead to the earth of the power lead.
• Connect the other test lead to a cover fixing screw, then the tap.
Warning ! The water may be boiling
• Verify that in every instance the electrical resistance does not exceed 1 ohm.
Warning! This appliance must be earthed
• Turn water supply ON. Water will flow into the Hydroboil, check connections for leaks. Wait approximately 5
minutes then pull the tap forward to test for water flow.
• Turn the mains electrical power ON only after the water flows freely from this outlet.
• After a short period, boiling water will be available and will be maintained close to boiling point thereafter.
Do not turn the power ON until the Hydroboil can dispense water from the tap outlet.
Commissioning
Note depending upon installation
connect to either the earth pin of the 3
pin plug, or the earth conductor of the
mains cable.