24
1
Zenith ZTG Series ATS, OPERATION, MAINTENANCE, AND INSTALLATION GUIDE
2.5 Sequence of Operations
2.5.1 Switching sequence / Automatic
2.5.1.1 SOURCE 1 Priority
(SOURCE 2 = Generator)
The switching sequence can be
summarized in the following steps:
An anomaly occurs on SOURCE 1
Override momentary S1 outage delay
Generator start
SOURCE 2 OK
Transfer from S1 to S2 delay
Pre-transfer signal on
Load shed signal on
Pre-transfer S1 to S2 delay
Load shed delay
Transfer switch (SOURCE 1) to
position O
Center-off delay (only with Delayed
transition I - O - II type)
Transfer switch (SOURCE 2) to
position II
Post-transfer S1 to S2 delay
Pre-transfer signal off
The re-transfer sequence can be
summarized in the following steps:
SOURCE 1 is restored
Transfer from S2 to S1 delay
Pre-transfer signal on
Pre-transfer S2 to S1 delay
Transfer switch (SOURCE 2) to
position O
Center-off delay (only with Delayed
transition I - O - II type)
Transfer switch (SOURCE 1) to
position I
Load shed signal off
Generator stop delay
Post-transfer S2 to S1 delay
Pre-transfer signal off
Generator stop
SOURCE 2 off

Table of Contents