5. Commissioning
Operation
42
Before starting up commissioning at site, please make sure below procedures
and requirements are fully meet.
• Mounting location is meet the requirements.
• All of the electrical wiring is firmly connected, including PV wiring, Grid wiring
and Earth wiring.
• The inverter setting has been finished accordingly to local standards or
regulations.
The method of active anti-islanding protection:
Shifting the frequency of the inverter away from nominal conditions in the absence
of a reference frequency (frequency shift);
4.5 Instructions of view inverter firmware version
4.4 Active anti-islanding protection
UP/DOWN Instructions of
view inverter firmware version
UP/DOWN Selection Inverter Info
Afore New Energy
Normal
Power=xx W
1s Delay
ENT
ENT
Inverter Info
Wifi Info
HNS5000TL
Version:M Vxxx
Version:S Vxxx
Version:C VXXX
For the viewing of the following functions, please refer to the steps in Chapter 4.3:
Country Grid Code/Region settings;
Power quality response modes settings;
Grid Protection settings;
Inverter firmware version.