5. Commissioning
Operation
42
Before starting up commissioning at site, please make sure below procedures
and requirements are fully meet.
• Mounting location is meet the requirements.
All of the electrical wiring is firmly connected, including PV wiring, Grid wiring
and Earth wiring.
• The inverter setting has been finished accordingly to local standards or
regulations.
The method of active anti-islanding protection:
Shifting the frequency of the inverter away from nominal conditions in the absence
of a reference frequency (frequency shift);
4.5 Instructions of view inverter firmware version
4.4 Active anti-islanding protection
UP/DOWN Instructions of
view inverter firmware version
UP/DOWN Selection Inverter Info
Afore New Energy
Normal
Power=xx W
1s Delay
ENT
ENT
Inverter Info
Wifi Info
HNS5000TL
VersionM Vxxx
VersionS Vxxx
VersionC VXXX
For the viewing of the following functions, please refer to the steps in Chapter 4.3
Country Grid Code/Region settings;
Power quality response modes settings;
Grid Protection settings;
Inverter firmware version.