6. Shut Down & Restart the Inverter
6.1 Shut down
Shut Down & Restart the Inverter
43
Commissioning Procedures
• Turn on the AC switch between inverter output and the public grid;
• Turn on the DC switch on the inverter;
• Turn on the PV switch of the system.
• Turn off the DC switch on the inverter.
• Turn off the DC switch between PV panels and the inverter (if any).
• Close the AC switch between the inverter and the public grid.
• Shut down the inverter according to Chapter 6.1.
• Start-up the inverter according to Chapter 5.
6.2 Restart
Note:
The inverter will be operable after minimum 5 minutes.
Periodically maintenance are necessary, please follow steps as below.
PV connection: twice a year
AC connection : twice a year
Earth connection: twice a year
Heat sink: clean with dry towel once a year.
Fault messages will be displayed when fault occurs, please according to
trouble- shooting table find related solutions.
7. Maintenance&Trouble Shooting
7.1 Maintenance
7.2 Trouble Shooting