Distribution Box
The distribution box (in the container) figure is shown as below:
Table 2 Distribution box swith discription
No.
Description
No.
Description
1
AC input
7
Exhaust fan
2
Air conditioner
8
BMS
3
PCS lighting
9
Container fan
4
Battery lighting
10
Camera
5
Socket
11
Camera
6
Emergency
4. Installation
Installation Precautions
The following sites are not allowed for installation:
- Sites which are salty and where humid air can penetrate.
- Flooded areas.
- Earthquake areas additional security measures are required here.
- Sites that are higher than 3000 meters above the sea level.
- Sites with explosive or potentially explosive atmosphere.
- Sites with extreme change of ambient temperature.
- Sites with highly flammable materials or gases.
Installation
If you don’t need the container, please skip to 4.2.2 directly.
Container Installation
4.2.1.1 Base Requirements
1. This container has been made based on the new 10'GP mark TEU dimensions;
2991*2438*2591 (long * wide * high).