C. Turn on NO.8 switch-BMS (see Table 2) of the distribution box:
D. After power-on the LED on the batteries and HV900112 starts flashing.
E. After two minutes, turn on the battery and PV switches of inverter by pushing up the
switch handles, the inverter will be powered on.
Figure 5-3 PV switch and battery switch in switch-off satus
F. turn on the load and diesel switches by pushing up the switch handles.
Figure 5-4 Load switch and diesel switch in switch-off satus
G. Normal system operation