19
B23P
-
C63
3.6 FLUE EXHAUST PIPE CONNECTION
e ue exhaust pipe must comply with local and national regulations.
ATTENTION
For this type of connection, the room follows
the same installation regulations for boilers
with natural draught
Connection to a combustion product evacuation pipe outside the
room, the combustion air is taken directly from the room where
the device is installed.
HEAD AVAILABLE AT THE BASE OF THE CHIMNEY
S (Exhaust) A (Intake)
Dp = 100 Pa -
A (Intake)
e maximum permitted length of the pipes is determined by the
head (Dp) available at the base of the chimney.
ATTENTION:
for the B23P type of connection, the
room follows the same installation regulations for
boilers with natural draught.
e boiler is approved for the draining settings described below:
ATTENTION
To congure the C63 you need to order the optional air
intake kit which includes instructions on application.
Separate ducts for combustion air intake and evacuation of combus-
tion products. (Commercial accessories)
HEAD AVAILABLE AT THE BASE OF THE CHIMNEY
S (Exhaust) A (Intake)
Dp = 100 Pa -
e maximum permitted length of the pipes is determined by the
head (Dp) available at the base of the chimney
ATTENTION:
The flue must comply with the standards in force
BS6644:2011- IGE/UP/10
3.6.1 FLUE EXHAUST MANIFOLD
CONNECTION
To secure the ue exhaust manifold use the nuts and
washers contained in the bag.
e ue point must be positioned on the rst straight
section, within 1 meter of the boiler.
To set up the ue inspection point, cut a Ø 21 mm hole
in the ue exhaust pipe, and install the inspection point
following the sequence provided.