All electrical installaon and service must be accomplished by a qualied electrician. Follow all naonal and local
electrical codes and ordinances.
“WARNING”
LOCK POWER IN OFF POSITION
All internal wiring has been factory installed and tested prior to shipping. Electrical installaon consists of
providing adequate machine power only.
Check building service to ensure correct voltage is available and those current requirements can be met
(according to nameplate (serial number), see below).
Install receptacle (provided) to properly protect building circuit. Select appropriate wire size and current
protecon to accommodate current requirements as shown on nameplate. Plug in power cable.
Clear all personnel from machine area. Ensure machine is clean and no tools, rags, or debris have been le
on conveyor belt or near cuers or drive mechanism.
Turn building service drop power on. Check voltage at installed receptacle.
Ensure area is clear. Turn key switch ON. Jog reverse. Check for proper motor rotaon. If rotaon is wrong,
unplug power cable. Check that power is OFF with voltage meter at panel. Remove any two power wires
from the motor starter, reverse and reconnect.
Clear area, turn on power and recheck rotaon.
Electrical installaon is complete.
Replace all guards.
ELECTRICAL INSTALLATION
NAMEPLATE:
Log your shredder specics here
MODEL NO. HP
PHASE SERIAL NUMBER
VOLTS CYCLE A.C. AMPS
JOB NUMBER