Operation Instructions
23
This setting can be done only when the unit is off.
This function can be memorized upon power failure.
2.4.18 Parameter Setting
[Operation Instructions]
At the commissioning parameter setting page, by touching “PARAM.”, it will access to the pages as shown below.
Page of Commissioning Parameters
At this page, select the desired option and then go to the corresponding page.
After that, by pressing “OK”, this setting will be saved and then the unit will run based on this setting; or by pressing
Cancel”, this setting will not be saved and quit.
No Full Name
Display
Name
Range Default Remark
1 T-HP max T-HP max 40~55°C 104~131°C 50°C /122°C
2
Cool run
time
Cool run
time
1~10min
3min
[2-way valve Off]
When “Cool run time” has expired
and temperature difference keeps
at the standby zone, the unit will
stop.
5min
[2-way valve On]
3
Heat run
time
Heat run
time
1~10min
3min
[2-way valve Off]
When “Heat run time” has expired
and temperature difference keeps
at the standby zone, the unit will
stop.
5min
[2-way valve On]
[Notes]
For parameters with different defaults at different conditions, once the current condition changes, the
corresponding default also will change.
All parameters at this page will be memorized upon power failure.