PRINCIPLE OF A CYCLE
The measurement cycle is made of 4 main phases: fill, stabilization, test, dumping.
A Pressure auto zero additional phase "5" can be placed at the start or at the end of a
cycle, depending on the requirement of the operator.
1 Fill phase
2 Stabilization phase
3 Test
4 Dumping (option)
5 Pressure auto zero phase
0 Waiting part connection in “Large Leak mode” (blowing air)
1 Fill phase
2 Stabilization phase
3 InfiniteTest time
4 Part is disconnected
5 Pressure auto zero