- 60 -
4.4.4.6 Paralleling
Prior to starting parallel operation of two generators,
following connections need to be made:
– Connect the communication cable between the
generators by plugging the adapter into socket
X30.
– Connect the load with the generator.
Go via the site distribution panel (to be installed
by the customer) to connect the generator(s) with
the load. Always connect generator with the load,
and never directly with second generator.
When paralleling, make sure to
disable the Earth leakage relay by
putting switch S13 into off position.