2. Connect ammeter for 0 20 mA to measuring points [4 and 5].
3. Turn potentiometer [1] clockwise to the stop.
4. Turn potentiometer [1] slightly in opposite direction.
5. Turn potentiometer [2] clockwise until output current starts to increase.
6. Turn potentiometer [2] in opposite direction until the following value is reached:
- for 0 20 mA approx. 0.1 mA
- for 4 20 mA approx. 4.1 mA
This ensures that the signal remains above the dead and live zero point.
7. Move valve to end position OPEN.
8. Set potentiometer [3] to end value 20 mA.
9. Approach end position CLOSED again and check minimum value (0.1 mA or
4.1 mA). If necessary, correct the setting.
70
SQEx 05.2 SQEx 14.2 / SQREx 05.2 SQREx 14.2 Control unit - electromechanical
Commissioning (optional equipment settings) ACExC 01.2 Intrusive

Table of Contents

Other manuals for AUMA SQEx 05.2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the AUMA SQEx 05.2 and is the answer not in the manual?

AUMA SQEx 05.2 Specifications

General IconGeneral
BrandAUMA
ModelSQEx 05.2
CategoryController
LanguageEnglish

Related product manuals