Installing the server
About this task
Use this procedure to install the server using the provided rail kit.
Before you begin
Warning:
• Before you begin, read and follow the safety instructions in your Safety, Environmental,
and Regulatory information document shipped with your system.
• To avoid injury, do not attempt to lift the system by yourself.
• Verify that the rack is installed according to the manufacturer's instructions and in
accordance with all local codes and laws. Verify that the rack is grounded in accordance
with local electrical code.
Note:
• Although not used frequently, Avaya customers are required to have a monitor, USB
keyboard, and USB mouse available for use by installation and servicing technicians.
• This rail kit is compatible with square, unthreaded round, and threaded round hole racks.
Procedure
1. Identify and separate the components of the Dell A7 ReadyRails II sliding rail assembly kit.
a. Two Dell A7 ReadyRails II sliding rail assemblies
b. Two hook and loop straps
Installing the server
December 2018 Installing the Avaya Converged Platform 120 Series 19