43
3000 Series Retail Operators Manual 108796 Rev C, 07/05
Bennett Pump Company
Site Audit Report
This form must be filled out and sent
in to Bennett to establish the equip-
ment warranty.
3000 Series Electronic Dispensers.
Bennett Pump Company
1218 E. Pontaluna Road
Spring Lake, MI 49456
Date of Audit
Model of Dispensers and Serial Numbers __ Site Information:
___________________________________ Site Phone Number ______________________
___________________________________ Site Name _____________________________
___________________________________ Site Address ____________________________
___________________________________ ____________________________
___________________________________ City ________________ State _____ Zip _____
___________________________________ Owned by _____________________________
___________________________________ Equipment Purchase Date __________________
___________________________________ Equipment Installation Date _________________
Dispenser mode being used - Stand Alone ______ Console ________ Mechanical Interface _____
Type of Interface Box being used if dispensers are in Console Mode?
Yes No Checklist
If connected to a console, is the maximum distance between the dispensers and the Inter
face Box less than 500 feet?
Are the field wires in metal conduit only?
Does each dispenser have a dedicated conduit?
Are the dispenser field wires Oil and Gas resistant, color coded, THHN, copper stranded?
Are the dispenser field wires continuous with no splices?
Is the resistance measurement between Ground and Neutral at the dispenser less than 1
ohm? Attach photo(s) (if possible) showing this measurement.
Are there no more than 2 dispensers on one breaker (maximum)?
Are the dispensers on dedicated breakers and NOT sharing power with any other equip
ment (sub pumps, motors, air– conditioners etc.)?
Do the supply tanks have fuel?
If it is a suction system, are all suction components installed per Bennett specifications?
If connected to a console, are the Interface boxes within 100 feet of the Point of Sale?
Is the vapor seal on the field wires in dispenser head installed?
Is the dispenser mechanically mounted to the island using securing bolts and shimmed for
squareness?
Is there an emergency cutoff shear valve mounted on each product inlet on remote dis-
pensers?
Is/are there satellite dispensers installed?
Are all dispensers on the same phase of power?
If this is a retail application, is there an emergency stop relay installed and working prop
erly for the fuel court area?
If this is a remote unit, are there RC Networks on the sub pump relays?
Have the meter calibrations been verified?
Was the Bennett Warranty statement reviewed with the station Manager / Owner?
Name of Owner / Manager? _________________________________________
Were all Bennett installation instructions in the Installation Manual followed? (If not, please
list on the next page).
Date of Installation
______________