Fig. 1-7 Fig. 1-8
2. Assembly FM Module:
2.1 Place FM on “HLD FM” surface(Fig. 2-1) and use “Clip FM” to fix FM(Fig. 2-2).
Fig. 2-1 Fig. 2-2
3. Assembly HSG ILL Module:
3.1 CM Assembly
I. Insert “Clip CM Side” first, and then place “Clip Front CM” to fixed-shaft of ILL SUB before
locking screw (Fig. 3-1, Fig. 3-2).
II. Assemble Mylar SUB HSG to HSG ILL well (Fig. 3-3).
III. Assemble CM to HSG ILL and to make CM contact three datum on the HSG ILL well (Fig.
3-3).
IV. Assemble” MYLAR CM” to the CMD firstly, “CLIP TOP CM”(with forceps) to the “HSG ILL”
(Fig. 3-4,).
V. To check and make sure “CLIP of CM” hooks the HSG ILL very Well (Fig. 3-5).
VI. Paste “Sponge tube AL” on cannelure of” HSG ILL” (Fig. 3-6).
3.2 FM Module Assembly
I. FM Module must be placed to fixed shaft and on the datum surface of “ILL SUB” and then
lock with screw well(Fig. 3-7).
Push on the left corner until lock
the screw well
Lock the screw well
Touch the side
surface
Clip FM hook
the punch points