4.3 Unpacking the boiler
Key to figures 22, 23, 24 & 25:
Table 16
▶ Remove outer carton [1] and place safely away from the working
area.
Fig. 22 Outer carton removal
▶ With the outer packaging removed and the inner sleeve [2] still in
place gently lay the boiler on its back.
Fig. 23 Laying boiler down
The boiler will lie at an angle to the floor to allow the boiler outer casing
[5] to be removed.
▶ The inner sleeve [2] opens as shown in figure 24.
▶ Remove the protective wrapping [4].
Fig. 24 Packaging removal
1. Undo but do not remove the two screws at the bottom of the boiler.
2. Undo the two screws at the top (see figure 25).
3. Remove the outer case [5].
Fig. 25 Outer case removal
NOTICE:
Transport protection covers
▶ Remove the internal transport packaging and protection covers from
the appliance.
CAUTION:
Before hanging the boiler!
▶ Remove the plastic strip fitted to pipes before hanging the boiler.
1 Outer carton
2 Inner sleeve (unwrap from front)
3 Packaging base
4 Protective wrapping
5 Boiler outer case