Starting Up
STARTING UP
In this manual, the word “battery” refers not to a single cell but to an entire backup system for an uninterruptable power
supply. In the BVM software, these battery systems are represented by *.bvm files, which contain the data which is
gathered the S5 SCM-600 controller and transmitted to your computer through cables or wires (serial, USB, phone, or
Ethernet).
1. Make sure the BVS hardware is configured properly
1. Make sure the BVS hardware is configured
properly..................................................................17
2. Make sure the SCM-600 is turned on and
connected ..............................................................19
3. Add the battery file(s) included on your BVM
software CD ...........................................................20
4. Make sure the hardware is communicating with the
software .................................................................21
5. Ensure that settings and readings are correct ..28
6. Enable remote communication............................39
Action How to do it Picture
1
Make sure the SCM-
600 is clean and free
of metal chips.
Remove the back cover and look inside to make
sure all metal filings were cleared away.
2
Make sure the
controller is
grounded.
Make sure the SCM ground wire is firmly connected inside the module and to the rack or
enclosure that holds it. (This picture shows ground wires for three SCMs.)
3
Make sure the
controller has power.
Make sure the SCM is plugged into an active outlet.
4
Make sure the
voltage sensors are
connected.
Make sure each VSL wire is connected to a quick disconnect tab on a battery terminal.
Make sure each VSL wire contains a fuse.