11
If the end connection leaks at the time of installation, remove pressure-
before attempting to tighten the seal.
The customer is responsible for ensuring chemical compatibility
between the owmeter and any uids being metered.
The meter will attain the temperature of the uid. Use caution when
touching the meter body to avoid burns.
Use appropriate bolts and hardware per ANSI B16.5 and, if applicable,
NACE MRO175 / ISO 15156.
Installation Procedure
1. Install a straight section of pipe on either side of the meter. This pipe
must be the same size as the meter end connection with a minimum
length of 10 pipe diameters upstream and 5 pipe diameters downstream.
For example, a owmeter with a 6-in. end connection requires 6-in. pipe.
The section of pipe upstream must be 60 in.; the section downstream
must be 30 in.
2. To create a cradle for the meter, assemble all-thread studs, nuts, (center-
ing rings, if purchased), and gaskets to connect the anges using only

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Cameron NUFLO EZ-IN Series and is the answer not in the manual?

Cameron NUFLO EZ-IN Series Specifications

General IconGeneral
BrandCameron
ModelNUFLO EZ-IN Series
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals