1 - RECEIVING THE UNIT
1.1 - General checks
■ Each unit has a data plate bearing an identication number. This number must
be included in all correspondence. Ensure that it is the correct unit by checking
the purchase order.
■ After unpacking the unit, please inspect it for any damage.
■ If any items are missing or in case of damage, specify this on the delivery slip
and inform the carrier by registered letter within 3 days of delivery of the unit.
1.2 - Unloading
■ The recipient shall be responsible for unloading the equipment and providing
the necessary handling equipment (see the section entitled "LIFTING
INSTRUCTIONS").
2 - SAFETY INSTRUCTIONS
■ Any operation must be carried out by qualied personnel using the appropriate Personal Protective Equipment (PPE).
■ Before any operation, read this guide carefully and keep it in a safe place. Safety information must be adhered to.
■ The units must not be run under operating conditions which are more restrictive than those it was designed for (pressure,
temperature, type and circulation of uids).
■ For units installed in European Community countries, ensure that the entire installation complies with the directives and
legislation in force.
■ Respect the instructions for using slings (see the labels on the unit).
■ To prevent any risk of accident, prohibit public access by clearly marking the work area.
2.1 - In an emergency
■ Switch off the electrical supply.
■ The process should not be jeopardised if the emergency stop devices are activated.
■ Switch off the fans.
2.2 - The 4 main risks
■ Lifting or positioning = Accident
■ Contact with the piping = Burns
■ Opening the electrics box = Electrocution
■ Removing the grilles = Injury